On most commercial fence projects, the install is not what holds up the schedule. The paperwork is. Before a crew can mobilize, the fence contractor has to show that what it plans to build matches the plans and specifications, and the document that proves it is the submittal package.

If you are a general contractor, owner, or project manager on a commercial job in Chicago or anywhere across the Midwest, knowing what belongs in a fence submittal helps you recognize a complete package, route it for review faster, and avoid the revise-and-resubmit cycles that quietly eat weeks off a schedule. Below, we walk through what reviewers expect to see, where the requirements come from, and why packages get sent back.

What Is a Commercial Fence Submittal Package?

A submittal package is the set of documents a fence subcontractor sends for review after a contract is awarded and before any material is ordered. Its job is simple: show exactly what will be built and exactly which products will be used to build it. The package usually travels from the fence sub to the general contractor, who checks it for completeness and forwards it to the architect or engineer of record. On larger projects, the owner’s representative or a security consultant may review it as well, especially when the fence is part of a site security plan.

The reviewer compares every drawing and data sheet against the contract documents, then returns the package with a stamp. The most common outcomes are approved, approved as noted, revise and resubmit, or rejected. Only the first two let the job move forward. Approved as noted means the reviewer accepted the package with minor corrections the fence sub must follow. Anything else sends the package back for changes and starts the review clock over.

That is why the submittal matters so much. Nothing gets ordered, fabricated, or installed until the fence scope is approved, and on many jobs, material lead times do not even start until approval comes back. A slow or incomplete package does not just delay the fence. It can push back site access, paving, landscaping, and every other trade that needs the perimeter finished.

For us, submittals are part of the core job, not an afterthought. They are a big part of the documentation standard we describe on our union and bid compliance page, and they are the reason our process is built around getting complete packages out quickly after award.

The Core Documents in a Fence Submittal

Every project spec is a little different, but most commercial fence submittals are built from the same core pieces.

CAD Fence Shop Drawings

Shop drawings are the center of the package. Good fence shop drawings are drawn to scale in CAD and show the fence layout, post types and spacing, post depth and footing details, fabric or panel details, and any topping such as barbed wire or anti-climb extensions. Gates get their own details showing dimensions, hinge orientation, swing or slide direction, and hardware. On gate-heavy scopes, these details often cover the full commercial gates and access control layout as well.

Fence Product Data Sheets

Each component gets a manufacturer data sheet: fabric or panels, line and terminal posts, rails, fittings, tension wire, barbed wire, gate frames, hinges, latches, and hardware. On a security or industrial job, this section alone can run many pages. Data sheets prove that the gauge, coating, and strength in the spec are what will actually be installed, which is one reason we source from established fence vendors rather than big-box suppliers.

Finish, Coating, and Color Information

When the spec calls for galvanized, vinyl-coated, or powder-coated material, the package documents the finish and color so the reviewer can confirm it matches the design intent. This matters most on commercial aluminum and ornamental fence frontages, where appearance is part of the spec.

Samples and Certifications, When Specified

Some specs also ask for physical samples, such as a fabric swatch or color chip, or for manufacturer certifications and warranty information. If the spec lists them, they belong in the package, and leaving them out is one of the easiest ways to earn a resubmittal. If the project requires a contractor workmanship warranty, that goes in the package too. We provide one on projects that call for it, typically for one to two years.

How to Find Fence Submittal Requirements in the Project Spec

The project specification tells you exactly what a fence submittal must include, so it is the first place to look. On most commercial projects organized in the standard CSI format, fencing falls under Division 32, Exterior Improvements. Chain link fences and gates, decorative metal fences, and other fence types each have their own section within that division.

Inside the fence section, look under Part 1, General, for a paragraph titled Submittals. It lists everything the reviewer expects to receive, such as product data, shop drawings, samples, qualification data, and certifications. A complete package answers every item on that list, in the order it appears, so the reviewer can check items off without hunting for them.

It is also worth reading the general requirements in Division 01. That is where the project defines how submittals are formatted, transmitted, and tracked, including whether electronic submission is required and how long the review period runs. A package that meets the content requirements but ignores the procedures can still be returned.

Addenda matter too. Changes issued during bidding can alter fence heights, gate counts, or materials, and a submittal built on an outdated plan set will be sent back no matter how well it is drawn. Before shop drawings start, we confirm we are working from the latest documents and every addendum. On larger jobs, such as perimeter security fencing for industrial and mission-critical sites, the spec can be detailed down to the number of barbed wire strands, so reading it closely up front saves time later.

Why Fence Submittals Get Sent Back on Chicago-Area Projects

Most returned submittals are not rejected because the fence is wrong. They come back because something is missing, unclear, or does not match the drawings. These are the issues we see most often:

  • Missing data sheets for small components. Fittings, tension bands, and gate hardware are easy to overlook, and reviewers notice when they are not there.
  • Shop drawings that are not to scale. A sketch or generic detail does not let the reviewer confirm spacing, heights, or clearances.
  • Post depth and footings left off. In northern Illinois and across the upper Midwest, frost is a real design concern, so reviewers expect footing depth and diameter on the drawings.
  • Gate details that do not match the plans. Opening sizes, swing directions, or hardware that differ from the site plan are among the most common comments on any fence submittal.
  • Substitutions that are not clearly flagged. If a proposed product differs from the specified one, it has to be identified as a substitution and supported with data showing it is equal.
  • Finish or color that does not match. A black vinyl-coated spec answered with a galvanized data sheet will come back every time.

Each of these can trigger a revise-and-resubmit cycle, and each cycle can add days or weeks while the package sits in the review queue. On commercial chain link fence projects with long runs and multiple gates, a single round of comments can hold up mobilization longer than the install itself takes. Catching these items before the package goes out is the fastest way to keep it moving.

Why Fence Submittals Often Take Longer Than the Install

A typical commercial fence install runs one to two weeks on site, and large footage can take three to four. The submittal process can easily take that long or longer once you add preparation, the reviewer’s turnaround, comments, and any resubmission. After approval, material lead times decide when a crew can actually start.

That gap surprises a lot of project teams, especially on fast-track jobs, which is why the front end deserves as much attention as the field work. The fence sub has the biggest influence on speed. A contractor that keeps standard details and vendor data on file can turn a complete package around quickly after award instead of building every drawing from scratch. That is how we work out of our Wheeling, IL office, where our estimating team and shop support projects across the Chicago suburbs, Illinois, Wisconsin, Indiana, Iowa, and the St. Louis metro.

GCs and owners can help, too. Send the fence sub every addendum before drawings start. Confirm the gate schedule early, since gates draw more comments than anything else in a fence submittal. If a substitution is on the table, settle it before the package goes out, not during review. And ask about lead times as soon as approval looks likely, so the start date is not a surprise.

Secure sites can add their own front-end steps. On data center perimeter fencing and other restricted facilities, site access requirements usually run alongside the submittal review, so planning for both early keeps the crew from waiting at the gate on day one.

Commercial Fence Submittal Checklist

Before a fence submittal goes to the reviewer, it is worth running through a quick final check. A package that passes these points has a much better chance of coming back approved on the first round:

  • Every item in the spec’s Submittals paragraph is included, in the order listed
  • Shop drawings are drawn to scale in CAD and built on the latest plan set and addenda
  • Post types, spacing, depth, and footing details are shown clearly
  • Every gate is detailed with dimensions, hinge orientation, swing or slide direction, and hardware
  • A data sheet is included for every component, down to fittings and gate hardware
  • Finish, coating, and color match the spec
  • Any substitution is clearly flagged and supported with data
  • Samples or certifications are attached if the spec calls for them

If any of these points are missing, it is faster to fix them before submission than to wait for comments. A few extra hours on the front end can save weeks on the back end.

Ready to Keep Your Fence Scope on Schedule?

A complete submittal package is what lets a fence crew start on time, and the work behind it starts before award. When you bring us into a project, we review the plans and specs closely at the bid stage, so we know what the submittal will need before the contract is signed. After award, our team prepares CAD shop drawings to scale and assembles product data for every component, so the package reaches your reviewer complete.

Whether it is a perimeter on an industrial development, game fence on a solar farm, or fencing for a public facility, the process is the same. If you have plans on your desk, send them our way. Request a bid from Pro Fence, and our estimators will get you a clear number built to your spec.

Fence Know-How From the People Who Bid It

Our estimators write about what they see every day: submittal packages, union and prevailing wage rules, temporary fence pricing, and what really drives a commercial bid. Have a project you want priced instead?

Contact Us Today
Like this article? Spread the word!
Related Posts

Union vs. Prevailing Wage: What It Means When You Hire a Fence Sub

Union vs. prevailing wage, explained for GCs hiring a fence sub: what each requires, why…

Temporary Fence Rental Cost: What Drives the Price on a Chicago Job

What drives temporary fence rental cost? Footage, 6 ft vs. 8 ft, stands vs. posts, rental…